Gas pipeline works

27 Feb 2017

The team at National Grid will soon be arriving to start work on the gas pipeline that runs though the North East Didcot site. The first phase of this work is planned to start at the end of February with vegetation clearance. This involves the removal of sections of hedgerow in preparation for the main works.

The main works, which are planned to start in mid-April, will be when the excavations will begin to divert the pipeline.

Minimising the level of disruption to our neighbours and people who use Lady Grove road is important to us. We aim to minimise the disruption to motorists.

If you have any questions, please get in touch with William Pender from our Community Relations Team. You can reach him on 0800 073 1047. The helpline is available between 7am – 7pm Monday to Friday and 7am – 1pm on Saturdays.